YearsBuilding & ConstructionRemarks
2001-2002
New Studios Building, CAA
Rafael Moneo, design architect
David Osler Associations, architect of record
 
2002
CAA Renovation of vacated ceramics, Metal and fiber departments for 2D and 3D design
Quinn Evans Architects

Fire safety upgrades were completed in thirty-three building on campus, including all of the dormitories
Siemans Building Technologies, Inc.
 
2003
Restoration of the West Wing roof at Cranbrook House
Allen Brothers Inc.
 
2004
Kingswood School Restoration (plans include the entrance plaza, restoration of Diana Fountain, interior carpet replacement and the Kingswood Lake pilot project)

Rainbow Fountain Restoration
Mitchell and Mouat, Architects
The Kingswood Lake project included dredging 20% of the lake, stabalizing the east riverbank at the Trellis Bridge and landscape improvements
2005
Phase II of Cranbrook House West Wing Restoration begins

Kingswood Entrance Plaza Restoration completed

Wenger Gym Renovation

Kingswood Roof Replacement and Drainage Improvement, Phase II begins
Quinn Evans, architect

Cranbrook Institute of Science Gateway Project (parking deck) begins
 



Snowmelt system installed
2006
West Entrance and Parking Deck, Cranbrook Institute of Science
Designed by Dan Hoffman; Smith Group, Architect
 
2007
Boys Middle School Renovation Project (plans include a new gymnasium, new entrance and renovation of the dining hall)
Duce Simmons Associates, architects

Quad Restoration begins
Mitchell and Mouat, Architects
The old gymnasium will become the new dining hall
2008
Cranbrook House stone wall restored
Cameron Stone, Inc.

Valley Way widened and realigned; Facilities boneyard and parking redesigned and paved
Sasaki Associates

Kingswood Auditorium Restoration

Kingswood Mezzanine Lounge Restoration
 
2009
Brookside Oriel Window restoration
Building Arts & Conservation

Brookside Garden Walkway and Tricycle Path
Walker Macy Landscape Architecture
 
 
2009-2010
CAA Museum Collection Storage Wing addition
Smith Group/JJR

CAA Museum and Library Renovation
Smith Group/JJR

Cranbrook Kingswood Middle School for Girls
Lake/Flato Architects

Cranbrook Tennis Courts Improvement
Johnson Hill Land Ethics Studio
 
2010
Cranbrook Road stone wall restoration
Cameron Stone, Inc.

Hoey Commons Room remodeled
Quinn Evans Architects

New Baseball Dugouts
DSA Architects

Brookside Tower Restoration
Building Art & Conservation